Peak House, Chatham
Project
Details |
 |
 |
| Client |
| Peak
Developers |
 |
| Contract
Type |
| JCT
98 with Contractors Design |
 |
| Main
Contractor |
| Howard
Construction (South East) |
 |
| Contract
Sum |
| £850,000 |
 |
| Contract
Duration |
| Summer
02-Spring 03 |
|
|
 |
The conversion of a Grade 2 listed Bank Building into
16 self contained flats for Town and Country Housing Association.
Works included sympathetic retention of fine plastered ceilings
cornices and columns and also a panelled board room. Structural
alterations and extensions involved the provision of a steel
framed mansard to form an additional floor.
JennerJones produced full working drawings and details
for the Developers and Contractors in this fast track
development in the centre of this Historic Maritime town.
 
|